Western Power solar connection rules and export limits, explained
Bigger systems are now allowed, but exports have to be managed or capped. What changed on 1 May 2026, and what it means for new systems, upgrades and existing owners.
Since 1 May 2026, a Perth home on Western Power's network can connect up to 30 kVA of solar and battery inverters on a standard single or three-phase connection. The old limit was 5 kVA. In return, a new or upgraded system has to be able to be remotely managed through your retailer if you want to sell exports under a product such as Synergy's DEBS. If you opt out, or the site has no stable internet, the system is set to a fixed 1.5 kW export limit instead.
Your installer lodges the application with Western Power, not you. Systems installed before 1 May 2026 that are not changed stay on the old rules. Adding a battery or another inverter counts as an upgrade, and then the new rules apply.
What changed on 1 May 2026
- Up to 30 kVA aggregate. Aggregate means every inverter on the site added together, solar and battery. The 5 kVA cap that shaped Perth solar for years no longer applies to standard connections.
- Remote connect and disconnect. To join an export product, the system must be able to be disconnected and reconnected remotely through your retailer, Synergy for most Perth homes. The communication standard behind this is called CSIP-AUS.
- A fixed 1.5 kW option. If you opt out of remote management, or have no stable internet, your exports are capped at 1.5 kW.
- Inverter settings. Inverters must comply with AS/NZS 4777.2 and be set to Australian Region B. That is set at commissioning, not something you change.
- Gateways. Where an inverter cannot communicate on its own, a gateway device can provide the connection.
The two export options, in plain terms
Remotely managed
The inverter, or a gateway beside it, talks to your retailer over the internet. That link is the condition for joining an export product such as DEBS, which pays 10c a kWh for exports between 3pm and 9pm and 2c at all other times. It also suits anyone planning a battery under the WA rebate, which needs you to join your retailer's virtual power plant. See our guide to DEBS.
Fixed 1.5 kW export limit
No remote link is needed. The system runs as normal, but no more than 1.5 kW goes to the grid at any moment. Anything beyond what the house uses, what a battery stores and that 1.5 kW is simply not produced. If you are weighing this option, ask your retailer what, if anything, the exported power earns before you decide.
For many homes the money gap between the two is smaller than it sounds. Most solar exports happen in the middle of the day, when DEBS pays 2c. What you use yourself is worth far more, at 33.2621c a unit on Synergy's Home Plan, which is why sizing for self-use matters more than the export setting. Our guide to what size solar system you need works through that.
What counts as an upgrade
Adding a battery or adding another inverter is an upgrade, so the new rules apply to the system once the work is done. That includes the export choice above and the inverter settings.
If you are on the old REBS buyback, which pays a flat 7.135c a kWh, check before you change anything. Making changes to your system can end your REBS eligibility, and you would be looking at the current DEBS rates instead. For some households that is fine. For others, especially those exporting a lot in the middle of the day, it is worth running the numbers first.
If you are only replacing a failed part, do not assume either way. Ask before the work is booked and we will tell you how the rules apply to your system.
Systems installed before 1 May 2026
If your system was connected before 1 May 2026 and you do not change it, it stays under the rules it was approved under. There is nothing to apply for and nothing to switch over. Keep it maintained and keep an eye on the monitoring. If output has dropped, a solar health check will tell you why.
Emergency Solar Management
Separate from export limits, Emergency Solar Management lets the grid operator curtail rooftop solar in rare emergencies, to keep the network stable. It is a backstop rather than something that shapes everyday output, and it is not the same thing as the fixed 1.5 kW limit.
Who lodges the Western Power application
The installer does. When people search for a Western Power solar application, they are usually expecting a form to fill in. You will not need to. What you do need to do is decide between remote management and the fixed limit, make sure the inverter location has a reliable internet connection if you choose remote management, and sign the paperwork your installer gives you. We lodge the application and set the system up to match what was approved.
The internet connection question
Remote management depends on the inverter staying connected. Inverters often sit in a garage or on a side wall, where home Wi-Fi is weakest. Before install day, check your phone's signal on your home network at the spot where the inverter will go. If it drops out, a wired connection or a Wi-Fi extender may be needed.
If your home has no reliable internet at all, the fixed 1.5 kW limit exists for exactly that case. It is a legitimate choice, not a penalty.
What this means for you
Buying a new system
You can go bigger than 6.6 kW, but bigger only pays if you use or store the output. Decide early whether a battery is likely, because the export choice and the inverter choice follow from it. Start with our solar installation page or the size guides, from a 6.6 kW system to a 10 kW system.
Adding a battery or panels
Your system becomes an upgrade, so the new rules apply. Check your current buyback first, confirm the existing inverter is up to it, and plan the internet connection. Our guide to adding a battery to existing solar goes through the order to do things in, and our battery storage page covers the install.
Leaving an existing system alone
Nothing changes for you. Your system keeps running under its original approval until you alter it.
FAQs
Questions on this
Do I need to apply to Western Power for solar?
Your installer lodges the connection application with Western Power for you. Your part is choosing between remote management and the fixed 1.5 kW export limit, and making sure the inverter has a reliable internet connection if you choose remote management.
What is the solar export limit in Perth?
For systems connected or upgraded since 1 May 2026, it depends on your choice. A system that can be remotely managed through your retailer can join an export product such as DEBS. One that cannot, or where you opt out, is set to a fixed 1.5 kW export limit.
Does adding a battery change my export setup?
Yes. Adding a battery or another inverter counts as an upgrade, so the new rules apply to the whole system after the work. If you are on the old REBS buyback, making changes can end that eligibility, so check first.
Is my existing solar system affected by the new rules?
Not if it was installed before 1 May 2026 and you do not change it. It stays under the rules it was approved under.